Weekly Traffic Report

NEW WORK

VICTORIA COUNTY: Highway 105

Highway 105 from .6 kilometres east of New Campbellton Road, westerly about 4.5 kilometres, will be reduced to one lane for asphalt concrete repaving. There will also be construction on a turning lane at the intersection of New Harris Road and Highway 105. Work will begin on June 4 and is expected to be completed on July 15. Delays can be expected from 6 a.m. to 8:30 p.m. Motorists are urged to use caution.

Local area office: 902-794-5120


CONTINUING WORK

Annapolis County: Phinney Bridge

Phinney Bridge on Old Mill Road, Wilmot, is reduced to one lane for repairs. The expected date of completion is July 10. Traffic control will be by traffic lights.

Local area office: 902-825-4880


Cape Breton County: Trunk 4

Trunk 4 from Loch Lomond Road to Middle Cape, Cape Breton Co., is reduced to one lane for upgrading, cold planning, gravelling and paving. Delays can be expected daily from 7 a.m. to 7 p.m. until completion on July 31.

Local area office: 902-563-2289


HALIFAX COUNTY: Highway 102

Highway 102 is reduced to one lane, north and southbound lanes between Lake Thomas Bridge and Highway 118, including portions of Exit 5 and off ramps for asphalt concrete cold planing and paving. Delays can be expected from 7 a.m. to 7 p.m. until work is completed on June 11. Motorists are requested to use alternate routes if possible.

Local area office: 902-424-4670


HALIFAX COUNTY: Highway 107

Highway 107 form Trunk 7 at Main Street at Forest Hills to Highway 118 overpass structure near Burnside, including ramps at Montague Mines Road and some ramps at the Highway 118 overpass are closed from 7 a.m. to 8 p.m. for asphalt concrete repaving until Aug. 31. Motorists can expect delays due to lane closures.

Local area office: 902-424-6144


HANTS COUNTY: Highway 102 Southbound

Highway 102 southbound from Exit 9 (Milford) to Exit 8 (Elmsdale) in Hants County is reduced to one lane for guard rail, cold planing, asphalt concrete paving and shoulder gravel work. Delays are expected daily from 6 a.m. to 7 p.m. The completion date for this work is Aug. 31.

Local area office: 902-883-9789


KINGS COUNTY: Horton Bridge, Highway 101

Horton Bridge, Highway 101, is restricted to one lane westbound for sandblasting and repainting. Motorists can expect delays until Oct. 31.

Local area office: 902-825-4880


LUNENBURG COUNTY: Highway 103

Ramps at Exit 13 and two at Exit 12 on Highway 103 have alternating lane closures for ditching, cold planing, paving and shoulder work. Delays are expected daily from 6:30 a.m. to 8 p.m. until completion on July 30.

Local area office: 902-543-7376